Capacity Constraint Effective 11-07-2011 at NGPL Interconnect Update

Notice Type: CAP_CONSTRAINT
Notice Identifier: 1041
Prior Notice Identifier: 975
Notice Effective Date: 11/18/2011
Notice Effective Time: 16:30:00
Notice End Date: 12/05/2011
Notice End Time: 09:00:00
Notice Subject: Critical, Capacity Constraint, 20111118, Golden Pass Pipeline LLC, 809259778
Required Response Indicator Description: N
Response Date:
Response Time:

Due to an unanticipated delay in the receipt of certain auxiliary facilities Golden Pass Pipeline (GPPL) continues to not be able to accept nominations for deliveries to the following location: Loc Name 805464 NGPL. This restriction will remain in effect until further notice. GPPL apologizes for any inconvenience and will update postings as more information becomes available. If you have any questions, please call Eric Purcell at 713.860.6336.